Kolkata Metro Line 6
'Line 6' (Orange Line) is a rapid transit metro line of the Kolkata Metro in Kolkata, West Bengal, India. It will connect New Garia with Netaji Subhas Chandra Bose International Airport via two major satellite towns of Kolkata metropolitan region, Salt Lake and New Town. It currently operates between Kavi Subhash and Hemanta Mukhopadhyay. This line will be one of the most important stretches of Kolkata Metro because it will connect the southern and the eastern parts of the city with Kolkata Airport. The total distance of this route will be 29.87 km (18.56 mi). It connects Line 1 at Kavi Subhash and will eventually connect Line 2 at Sector-V and Kaikhali and Line 4 at Airport.
History
[edit]This project was sanctioned in the budget of 2010–11 by Mamata Banerjee with a project deadline of six years.[4] The execution of this project has been entrusted to RVNL at a cost of Rs 3951.98 crore. It will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport and will have 23 elevated stations, 1 underground station and 1 at-grade. The terminal Airport station being the underground one.
Work for construction of the terminal station at New Garia for the 29.87 km (18.56 mi) Kavi Subhash-Biman Bandar (via Rajarhat) metro project finally resumed on 14 February 2017 with Rail Vikas Nigam Ltd (RVNL) demarcating the plot they require for the purpose.
The work has been delayed for years due to multiple issues. At first AAI objected the station above the ground, stating that this could be a threat for air traffic. Many underground utilities, power sub-station and water treatment plant had to be shifted. Encroachments and Land acquisition problems held up the project for multiple times.
The 5 km (3.1 mi) stretch from New Garia to Ruby Hospital was expected to start from 2018.[5] As of now, the station and associated metro viaduct connections are fully completed with trail runs being conducted over this and other phase 1 stations. RVNL planned to launch the metro over this truncated route before this year's Durga Puja, but was postponed due to signalling issues.[6]
After lot of hardships and developmental work, the Kavi Subhash-Hemanta Mukhopadhyay section of Kolkata Metro Line 6 was inaugurated on 6 March 2024 by Prime Minister Narendra Modi, along with the truncated sections of Taratala-Majerhat under Line 3 and Esplanade-Howrah Maidan under Line 2.[7] A week later after inauguration and a day after commercial run started on Kavi Subhash-Hemanta Mukhopadhyay section, RVNL announced the completion of a 76 m viaduct gap after construction of a single-span open-web girder steel bridge over Tagore Park culvert. This completed the viaduct up to Beliaghata metro station.[8] Trial runs have started over Hemanta Mukhopadhyay-Beleghata metro station and this stretch is planned to open in late 2024.[9]
Route
[edit]The stations are named after eminent Bengali personalities.[4][10][11] and will have 22 elevated stations, 1 underground station and 1 at-grade. The terminal Airport station will be the underground one. This station will also have a yard and it will be the largest underground facility of India and city's first. It will be 550 m (1,800 ft) long and 41.6 m (136 ft) wide and will facilitate stabling and reversal of rakes, but it will not be a carshed. One can interchange to Line 4 at Dum Dum Airport, Line 2 at VIP Road (Haldiram) and Salt Lake Sector V and Line 1 at Kavi Subhash. At Kavi Subhash, Rail Interchange will be also available (Sealdah South Section).
On 4 January 2021 the state government decided to rename 9 metro stations in New Town area to their more prevailing names rather than using the old ones which were given during the planning phase. The state transport department has informed Housing Infrastructure Development Corporation (HIDCO) of the new names of the proposed nine metro stations between Nazrul Tirtha at the entry of New Town from Salt Lake Sector V till Chinar Park, the last station on the line before it turns right on VIP road towards Kolkata Airport.[12]
Line 6 (Orange Line)[13] | ||||||||
---|---|---|---|---|---|---|---|---|
# | Station name | Location | Phase | Opening | Connections | Layout | Notes | |
English | Bengali | |||||||
1 | Jai Hind | জয় হিন্দ | Kolkata Airport | 4 | Under construction | Yellow Line • Jai Hind (U/C) |
Underground | |
2 | VIP Road | ভি আই পি রোড | Teghoria | Green Line • Haldirams (Planned) ---- |
Elevated | |||
3 | Chinar Park | New Town | 3 | |||||
4 | City Centre-2 | সিটি সেন্টার-২ | ||||||
5 | Mangaldeep | মঙ্গলদীপ | Also known as Akanksha 5-point crossing | |||||
6 | Eco Park | ইকো পার্ক | Also known as Nawabpur | |||||
7 | Mother's Wax Museum | মাদার্স ওয়াক্স মিউজিয়াম | ||||||
8 | Shiksha Tirtha | শিক্ষা তীর্থ | Also known as Kala Kshetra | |||||
9 | Biswa Bangla Convention Centre | বিশ্ব বাংলা কনভেনশন সেন্টার | Also known as Narkelbagan / Rabindra Tirtha | |||||
10 | Swapnabhor | স্বপ্ন ভোর | ||||||
11 | Nazrul Tirtha | নজরুল তীর্থ | Also known as Newtown Bus Stand | |||||
12 | Nabadiganta | নবদিগন্ত | Salt Lake | Also known as Bidhannagar Limit | ||||
13 | IT Centre | আই টি সেন্টার | 2 | Green Line • Salt Lake Sector-V ---- |
Located near IT Hub of Kolkata | |||
14 | Nalban | নলবন | Serving Nicco Park | |||||
15 | Gour Kishore Ghosh (Chingrighata) | গৌর কিশোর ঘোষ | Also known as Chingrighata / Sukanta Nagar | |||||
16 | Beleghata | বেলেঘাটা | Metropolitan | Also known as Tangra Metropolitan Township | ||||
17 | Barun Sengupta (Science City) | বরুণ সেনগুপ্ত | Dhapa/Mathpukur | Also known as Metropolitan | ||||
18 | Ritwik Ghatak (Bantala Road) | ঋত্বিক ঘটক | Uttar Panchanagram | |||||
19 | VIP Bazar | ভি আই পি বাজার | VIP Bazar | |||||
20 | Hemanta Mukhopadhyay (Ruby Hospital) | হেমন্ত মুখোপাধ্যায় | Ruby Island | 1 | 6 March 2024 | Elevated | Also known as Kasba Golpark / East Kolkata Township | |
21 | Kavi Sukanta (Kalikapur) | কবি সুকান্ত | Kalikapur | |||||
22 | Jyotirindra Nandi (Mukundpur) | জ্যোতিরিন্দ্র নন্দী | Mukundapur | Also known as Singhbari | ||||
23 | Satyajit Ray | সত্যজিৎ রায় | SRFTI / Hiland Park | Bengal Ambuja Bus Stop | Also known as Chak Garia / Ajoy Nagar | |||
24 | Kavi Subhash | কবি সুভাষ | New Garia | Blue Line • Kavi Subhash ---- |
At Grade |
See also
[edit]- Kolkata Metro
- List of Kolkata Metro stations
- Kolkata Metro rolling stock
- Lists of rapid transit systems
- Trams in Kolkata
- Kolkata Light Rail Transit
- Kolkata Monorail
- Kolkata Suburban Railway
References
[edit]- ^ "New System Map of Kolkata Metro".
- ^ "In addition to the underwater metro, the Prime Minister will also inaugurate the Kavi Subhash - Hemanta Mukhopadhyay Metro section".
- ^ "CAF to supply Kolkata metro trains".
- ^ a b "Rail set to take over East-West". The Telegraph. Calcutta, India. 8 February 2011. Archived from the original on 13 February 2011.
- ^ "Metro sets June 2018 date for New Garia-Ruby line". The Times of India.
- ^ Staff Reporter (25 August 2023). "Successful Speed Trial Conducted on Hemanta Mukhopadhyay-Kavi Subhas Metro Stretch". Metro Rail News. Retrieved 19 September 2023.
- ^ "Hope for ops start of three new Metro links in March first week". The Times of India. 19 February 2024. ISSN 0971-8257. Retrieved 21 February 2024.
- ^ "Traffic starts moving along Tagore Park western flank". The Times of India. ISSN 0971-8257. Retrieved 16 March 2024.
- ^ "Metro goes beyond Ruby, reaches Metropolitan on maiden trial run". The Times of India. 29 March 2024. ISSN 0971-8257. Retrieved 29 March 2024.
- ^ "New Garia to Biman Bandar via Rajarhat Metro extension".
- ^ "Kolkata Metro Line 6".
- ^ Mondal, Biswadeep (4 January 2021). "West Bengal govt renames nine New Town Metro stations". Times of India.
- ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 7 March 2024.